Project
On
a much-cherished Island in the heart of Virginia Beach, a custom residence was
showing signs of settlement.
Engineers were called to evaluate the problem.
Job
Description

During construction of the building the
intermediate pilings and grade beams called for on the structural drawings
were
excluded. The floating pier and
footings that were
installed had settlement of as much as 6”.
In addition, the right front corner of the house
and masonry fireplace had 1” of settlement. A soils investigation showed that organic peat
materials existed down to a depth of
8' below grade. This home was
built on a crawl space with a height of 36”.
Solution
- Magnum Piering
Crawl
Space Piering
The contractor proposed the installation of
modified 60 kip duty Helix piers to replace the failed
footings
and piers. The helix piers were
manufactured to 24” lengths with a 12” flight to allow installation in the
low crawl space. Each girder line
required 5 helix piers with an ultimate capacity of 16 kip and a working capacity of 8 kips.
Average pier depths were 14’ below grade.
After installation 60 kip wall pier caps were installed with a 12” diameter cast in place pier cap
to the new 12”X10” laminated girder. After
concrete placement and a 10-day curing period the interior was lifted and loaded onto the piers, then
shimmed to the correct floor beam deflections.
Exterior Piering
Due
to the affected area being supported on pilings with grade beams, a decision was
made to stabilize this area with 6 Magnum Standard duty piers.
Each section was a standard 5’ length, galvanized, with a 10” and
12” diameter flight. Each had dual cutting edges with moment-balanced blades for
cutting through debris and to lesson wobble during installation. Average pier depth of 13' with ultimate capacity of 38 kips and a
working capacity of 19 kips.

Contact Information
-
Phone: 757-546-0190
-
Fax: 757- 546-0318
-
- E-Mail